This morning, the Federal Circuit released two nonprecedential opinions. One comes in a patent case appealed from the Southern District of California; the other comes in a government contract case appealed from the Armed Services Board of Contract Appeals. Here are the introductions to the opinions.
DS Advanced Enters. v. Lowe’s Home Centers, LLC (Nonprecedential)
DS Advanced Enterprises, Ltd. (“DS Advanced”) owns U.S. Patent No. 11,054,118 (“’118 patent”), which relates generally to a light-emitting diode (“LED”) light fixture that attaches either to a ceiling or to a recessed light fixture. DS Advanced sued Lowe’s Home Centers, LLC (“Lowe’s”) for infringement of the ’118 patent.
The district court granted summary judgment of noninfringement and denied DS Advanced’s motion to alter or amend the judgment. The district court also sanctioned DS Advanced’s attorney for violating a stipulated protective order. Later, the district court denied the motion for attorneys’ fees and costs filed by Lowe’s.
DS Advanced appeals the judgment of noninfringement and the denial of its motion to alter or amend. DS Advanced’s attorney appeals the sanctions order. Lowe’s cross-appeals the denial of fees. We affirm the district court in all respects.
Walsh Turner Joint Venture II v. Secretary of the Army (Nonprecedential)
Walsh Turner Joint Venture II (Walsh) contracted with the United States Army Corps of Engineers (Corps, or government) in August 2021 to build a new Veterans Affairs Medical Center (VAMC) in Louisville, Kentucky, in exchange for about $840 million. On September 9, 2021, the President of the United States issued an executive order that broadly required employees of government contractors and subcontractors to be vaccinated against COVID-19. On November 3, after Department of Defense implementation of the executive order, the Corps sent Walsh a request for a proposal (RFP) to address recovery of contractor costs of the new obligations, with a cover letter using the word “mandatory.” On November 30, a district court preliminarily enjoined the executive order in Kentucky as likely unconstitutional and statutorily unauthorized. Two days later the government rescinded the obligations and RFP.
Shortly thereafter, Walsh argued to the Corps that the government, by its actions based on the executive order, had made a material change to the terms of the construction contract, warranting damages to compensate for resulting increases in raw-material and labor costs. The Corps denied relief. Walsh then sought relief from the Armed Services Board of Contract Appeals, but the Board dismissed Walsh’s complaint for failure to state a claim. Appeal of Walsh Turner Joint Venture II, ASBCA No. 63665, 2025 WL 1554019 (May 8, 2025) (Decision). Because Walsh’s complaint sufficiently alleges a constructive change, we reverse and remand for further proceedings, including full analysis of the government’s sovereign-acts-doctrine defense, which the Board did not address.