Oracle America, Inc. v. United States

 
DOCKET NO.
OP. BELOW
SUBJECT
Gov. Contract

Question(s) Presented

1. “Whether a bid protest that establishes a violation of federal law may be denied for ‘harmless error’ based on a rationale not present in the administrative record.”

2. “Whether, in resolving a bid protest that establishes a violation of the criminal conflict-of-interest statute, 18 U.S.C. § 208, the Federal Circuit can enforce the contract based on deference to an agency’s assessment that the criminal violation did not taint the procurement.”

Date
Proceedings and Orders
February 19, 2021
Motion to extend the time to file a response is granted and the time is extended to and including April 5, 2021.
March 29, 2021
Motion to extend the time to file a response is granted and the time is further extended to and including May 3, 2021.
May 18, 2021
DISTRIBUTED for Conference of 6/3/2021.
May 19, 2021
Response Requested. (Due June 18, 2021)
June 30, 2021
DISTRIBUTED for Conference of 9/27/2021.
October 4, 2021
Petition DENIED.