Kurkjian v. Secretary of the Army

 
DOCKET NO.
OP. BELOW
SUBJECT
Pro Se

Question(s) Presented

1. “Whether a Court can neglect the legal and statutory obligations of an agency to adhere to a signed contract and the referenced clauses; by saying the contract was ‘effectively’ completed?”

2. “Whether a Court can rely on ‘facts’ that are in conflict with the testimony of the Contracting Officer?”

3. “Whether the Court erred in discounting evidence that the Contractor suffered a reprisal for disclosing information about violations of law and other conditions that she believed posed a specific and substantial danger?”

4. “Whether ‘bad faith’ entitles a contractor to the lost profits of the unexercised option years stipulated in a signed contract?”

Posts About this Case

Date
Proceedings and Orders
March 10, 2022
DISTRIBUTED for Conference of 3/25/2022.
March 28, 2022
Petition DENIED.
May 3, 2022
DISTRIBUTED for Conference of 5/19/2022.
May 23, 2022
Rehearing DENIED.